Trench Wars: Developer should not have started development without Listed Building Consent

New Craig in an Autumn sunset: Grade A listed building

People in the local community have been challenging the fact that the developers had started work on the old consent without Listed Building Consent – which ran out in 2007. The planning consent for the Arts Faculty Building stated clearly that work could not start without it – and yet the planning department waved this aside, insisting that Listed Building Consents and Planning Consents were different processes – and therefore it wasn’t needed.

Councillors who were contacted merely circulated a statement from David Leslie (Development Management Manager in the council) – which said the same thing.

View of Craighouse from Braid Hills

View of Craighouse from Braid Hills

Well, they are wrong.

According to the The Scottish Historic Environment Policy (considered the authoritative document by the Scottish Planning Policy outlining the Scottish Government’s policy on listed buildings) it states clearly and unmistakably in good old black and white:

“Where both LBC & planning permission are required the applicant must obtain both before work can commence.”

(Our underscore)

So, the residents who wrote were right all along.

We want some answers, Councillors, and we want proper answers this time, not just circulated statements that are incorrect fob offs.

(Update: The source document from Historic Scotland is here: http://www.historic-scotland.gov.uk/index/heritage/policy/shep.htm. The relevant section is Annex 9)

Posted in Planning process | 5 Comments

The 10-year old university building consent: Update

We made a formal complaint to the council about the “activation” of a decade-old consent at Craighouse. We have a reply from the council now. We will be taking this further. Here is an explanation of our complaint, the current situation, and their response. This is an extremely complicated situation, so we will try to keep it simple!

Click on the image above to download the Council’s letter of response

Ever since Napier University sold Craighouse to Mountgrange, there has been vague talk of a prior planning consent, dating from 2001. Some pictures of the proposals were shown to the public. But, when we tried to find out more about this consent, we found very little paperwork. The actual consent itself, and the “Section 75” legal agreement attached to it was neither online nor in the Council’s public archive. This is unusual, as planning consents are public documents. When we asked more about it, we found nothing. Napier – despite FOIs –  gave us nothing. So we were shocked to discover, in June of this year, that (officially, at least) work had “already started”, and then stopped, as suddenly as it had begun.

What followed was weeks of investigating, pushing planners, writing letters, visiting the archives, and Freedom of Information requests to finally get hold of the paperwork that should have always been public in the first place.

The hidden paperwork, and the lengths we had to go to in order to obtain the documents that should have been public, is something we will write about further.

Just a part of the area that council planners have given consent to become a construction site (most of the area in front of New Craig)

The 80,000sq ft building in this consent would be sited opp New Craig – taking out the green space on the right here – and extending back into the woodland behind – Craighouse Wood. This whole area could be cleared and woodland felled. This is one of two large development sites that would be granted by this consent.

The latest response from the council is now that the paperwork “was considered to be available to the public”. What does this mean? All it says is that someone (unnamed), somewhere in the council, at some point in the past, thought that the paperwork was public. Not that it was public. Nor even necessarily that everyone at the Council believed it to be public.

Given the amount of evidence that we have now obtained, showing that this planning consent was hidden, and known to be unavailable publicly, we think it right that we challenge the validity of the consent.

What would this planning consent allow?

It is important to remember that this consent, if allowed to stand, would be granted in perpetuity. This is plainly wrong for such a permanent consent to be granted for a university building when the university has sold the site for a housing development.

Just part of green area and woodland that would become carparking – c. twice the spaces of current carpark

this green area would become part of a large carpark (c. twice the spaces of the existing entrance carpark)

The consent, if allowed to stand, would give Mountgrange the permission to create 2 large construction sites in woodland at Craighouse. One site would be in the woodland opposite the current car-park, where the green space would be cleared for a large carpark (with around double the spaces of the current car-park). The other site is on the greenspace and woodland opposite New Craig and behind Bevan. This site is for a large 80,000sq ft university building. Mountgrange could fell trees, clear woodland,  then leave both as construction sites indefinitely.

Demolition of the bus station for the Caltongate project

Why would they, you ask?

To answer this question, it may be helpful to look at their last project in Edinburgh, Caltongate.

Artists protesting at being evicted at the proposed Caltongate site

Early in the Caltgongate project, Mountgrange demolished the existing bus station (which had been used as local markets and artists’ studios) before presenting their plans to the council and public. Soon after obtaining outline planning consent at Caltongate, Mountgrange went into administration and the site has been a gap site ever since.

The Caltongate gap site as left by Mountgrange

It is worth noting that Mountgrange call Craighouse “strategic land”. A description by an expert lawyer from Morton Fraser says that Strategic Land usually means a 5 to 30 year timescale. It is not necessarily for development – sometimes it is held and sold on and sometimes they look to get consent for as much housing as possible – and sell it on. (Rather similar to what Napier seems to have achieved with the university building consent.)

We can’t know what Mountrange’s intentions are for the site, but we do know that they went to great lengths to try and enable this old planning consent for a building they have shown no intention of developing. Why obtain a planning consent if there is no intention to develop it? What about in 5 years? Or 10 years? Look at how a consent from 2002 has already come back into the picture 10 years after the planning committee made a decision for the requirements of the university, but now the consent is being used for a totally different reason. A consent that if this decision is not reversed will last in perpetuity and allows the site to be spoiled and left a mess.

And even if Mountgrange do not do any woodland clearing work with this consent, they can easily sell the site onto someone else who does. Why has the Council allowed this to happen on such an important and protected site?

There will be nothing we can do about it in 5 or 10 years. We must do something about it now.

Why did the council do this?

Earlier correspondence by the council tried to suggest that the planning department had no choice but to accept that Mountgrange could start development, and had started development. That line is not repeated in their latest letter, where they make it much clearer that the council chose to allow this development to start.

On the issue of whether the development had actually started, they state:

“Planning is of the view that the trench does constitute a lawful start to the development and we do not accept your conclusions”

Our letter to the planning department presented the law on starting development. The law makes it clear that a lawful start must be a material operation. Digging a trench and then filling it in again is not a material operation. It is not construction. It isn’t even in the foundations of where the building was to be. It is not a lawful start. This is a case of the council accepting work as a legitimate start to the development, despite it being a pointless operation.

On the issue of whether the development undertaken on site was lawful, they state:

“The only condition referred to in your letter which is suspensive is condition 4 relating to archaeology. The other conditions are not suspensive.”

The argument of whether the conditions are “suspensive” or not is a legal argument, on which they are silent. However, they admit that the archaeological condition was suspensive. And yet they are silent on the fact that the consent stated that the archaeological plan needed not just to be submitted, but implemented before work could start. This would have involved a number of archaeological trenches being dug. None of this was done.

On the other conditions, they accept that the work was undertaken against the conditions of the planning consent, but because those other conditions were not (in their words) “suspensive”, then it doesn’t matter that the work didn’t comply with the other conditions on the consent.

The council are also silent on the issue of why they accepted a set of tree-protection plans one week, and then allowed the developer to completely ignore those same plans the next week. Are the council suggesting that plans submitted to the planning department are irrelevent and can be ignored at will?

Does this not make a mockery of the whole system?

What we want from our elected representatives

We want any planning process at Craighouse to go through the normal legal processes, with planning applications and consents available to the public, so that the public can object.

We want proper transparency and paperwork to be made fully available.

We want the politicians to stand up for their pledges to protect the site, their pledges about green space in this city and stand next to the local community in calling for this decision to be reversed.

If The Craighouse Partnership want to put in their proposals for their housing development -go ahead. We have been waiting a year and…nothing (strategic land, anyone?) But this is not the way to do it – trying to activate inappropriate historic consents with hidden paperwork, incorrect process and no lawful start.

We call on The Craighouse Partnership and the Council to start again. Do this properly. Put forth reasonable plans that stand or fall on their own merits. No more behind the scenes maneouvrings of the planning system or reliance on “loopholes” that do not exist in law.

We will be replying to the planning department letter and taking the complaint to the Ombudsman, so this careless decision can be reversed.

Or what happened at Caltongate could happen again at Craighouse.

Posted in Planning process | 4 Comments

Planning Article 3: Skyline Views Out from the Site

Continuing our series of planning articles – here is our second skyline article – after Views Into the Site and our Introduction to Planning Designations and Documents. (Visit our key issues section on the menu for the rest of this series that we are posting over the next while.)

The views out of the Site are also outstanding and protected, including views into the World Heritage site and a panorama that includes: the castle, the Firth of Forth, the Lomonds, Arthur’s Seat, Blackford Hill and all the way to North Berwick Law.  These can best be appreciated from the orchard. The issue of impact on views of Edinburgh’s skyline is a major material planning consideration.

Magnificent views to Arthur’s Seat and North Berwick Law (above) and (below) superb panoramic views extend from the Firth with the Lomonds behind to Blackford Hill – with the castle, the World Heritage Site, Arthurs Seat and all the way to North Berwick Law, between.

Protected View to the Castle
The Edinburgh Skyline Study identifies Easter Craiglockhart Hill as a Key view to the Castle (S4b) which cannot be seen from the summit but from the open area to the south of the campus.

The Cockburn Association believes the views from where the developers want to build are the most important of the whole site:

“The path has views south to the Pentlands and spectacular views to the north east across the city to Arthur’s Seat and Edinburgh Castle; the design of the boundary wall allows people to stop, sit and enjoy these views. The view afforded to the city centre from this vantage point is better than that from the summit of Easter Craiglockhart Hill.

The parkland was created as the setting of the Asylum as is clear from the route of the paths established round the perimeter, whether for access or for patients to walk. Building on the south or east of the open grass would change the historic setting to an urban character when it should remain semi-natural.” (Letter by The Cockburn Association)

Relevant policies and key documents:

  • ECLP Policy OS1 (Protection of Open Space) presumes against loss of open space unless it can meet five tests. The first test is that: ‘There will be no significant impact on the quality or character of the local environment’.
  • The Edinburgh Survey of Gardens and Designed Landscapes notes that the site is significant for its listed buildings and associated social history but particularly for its presence within views of Edinburgh and its accessibility for locals.
  • The Edinburgh Landscape Character Assessment describes it as a “prominent urban hill”, part of a series of distinctive hills in Edinburgh that contribute to form the character of the city.
  • Env 11 (Landscape Quality) presumes against development which would damage or detract from the character or appearance of the AGLV, prominent ridges or other important topographical features.
  • The Craiglockhart Hills Conservation Area Character Appraisal states that the essential character of the area is derived from its significant cluster of Victorian institutions set within a very high quality landscape and topographic setting.
  • Edinburgh Skyline Study identifies Easter Craiglockhart Hill as a Key view to the Castle (S4b) which cannot be seen from the summit but from the open area to the south of the campus.
  • The Craiglockhart Hills Conservation Area Character Appraisal recognises: “The far-reaching and panoramic views.’
Posted in Planning process, Uncategorized | Tagged , , , | Leave a comment

Friends of Craighouse Official Complaint to the Council

In June 2012 The Craighouse Partnership claimed to have activated a consent – over ten years after the planning committee agreed it –  for an 80,000 sq ft university building by digging a “trench” and filling it in again. The Council waived associated pre-conditions that would have protected the site. The Craighouse Partnership are now applying to change the conditions further so as to delay, maybe indefinitely, having to pay the associated costs to the Council to the tune of £180,000.

We met with senior planning officials who confirmed that this consent would allow removal of mature woodland, the putting in of carparking and infrastructure. In short, the site could be left in a mess without any obligation to build the associated institutional building. Although they say this could also be built. This consent would last in perpetuity.

We are also unhappy about the lack of transparency and unavailability of paperwork that should have been in the public archives.

The Friends of Craighouse have prepared a formal complaint to the Council which was sent earlier this week and is copied in full below.

————

Dear City of Edinburgh Council,

RE: Complaints pertaining planning permission 01/04599/FUL and 01/04599/LBC

In reference to the above planning consent, we wish to invoke the Council’s formal complaint procedure to raise several heads of complaint.

Background

On or around March 2010, Napier University sold the Craighouse estate to an off-shore investment holdings. In broad terms, the estate is now administered by Mountgrange Investment Management LLP (MIM) which has formed a development consortium, the Craighouse Partnership (CP), comprising Mountgrange, Sundial Properties (SP) and Edinburgh Napier University (ENU). The CP seek to renovate the existing buildings and build extensive new build property within the estate.

Recently, the Friends of Craighouse (FoC) discovered that CP were attempting to activate planning consent 01/04599/FUL at the “eleventh-hour”. Ostensibly, the City of Edinburgh Council (CEC) appear to have acceded to the requests made by the CP through their agents Montagu-Evans (ME). This is confirmed by various documents held on the CEC online planning portal, a statement form John Bury and a letter from David Leslie.

The FoC are challenging the CEC’s decision to approve the CP’s position that consent was activated and we fully expect the CEC to confirm the correct position that 01/04599/FUL was not activated before it expired.

The FoC are challenging the provision of a notice by CEC to ME discharging the suspensive conditions attached to 01/04599/FUL when several of those conditions had plainly not been met.

The FoC are also challenging the competence of the original decision notice granting consent for 01/04599/FUL to ENU in 2007.

Finally, the FoC are seeking appointment of an impartial third-party auditor to investigate the CEC’s handling of all non-trivial planning applications concerning the Craighouse estate.

Interest and Standing

The issues at hand are of significant importance to the local community surrounding the Craighouse estate. Indeed, the administration of the planning process surrounding the Craighouse estate is of significant importance to Edinburgh and Scotland at large.

In light of the recent Supreme Court decision in AXA General Insurance Limited and others (Appellants) v The Lord Advocate and others (Respondents) (Scotland) 2011, it is plain to see that an action for Judicial Review by either a relevant individual or community group, affected by the CEC decisions in relation to Craighouse, would be competent before the Court of Session. Therefore, by the same reasoning, the CEC cannot decline to entertain the complaint outlined herein.

The FoC represent many of the people in the local community[1] and are also acting in the public interest in a general manner to ensure the CEC lawfully discharges its duties as concerns the Craighouse estate.

The planning or other decisions made by the CEC in relation to Craighouse will affect the local community in a material and substantial manner. Decisions have potential to:

  1. deprive the local community of amenity of the estate for walking and recreation;

  2. cause irreparable damage to an estate of significant historical value both to Edinburgh and more specifically Scotland’s pioneering position in mental health care during the time the Sydney Mitchell buildings were commissioned;

  3. infringe or obscure views into the estate and out from the estate, which is currently an amenity to the people of Edinburgh and form part of the character of the city;

  4. change in an undesirable manner views into the estate from areas of Edinburgh that are currently protected by UNESCO status;

  5. cause adverse affects to wildlife and disrupt a wildlife corridor;

  6. allow development on the estate despite no prospect of completion due to lack of listed buildings consent and potentially also restricting public access to the site;

  7. allow destruction of highly valued landscape and setting; and,

  8. set a precedent for the future which could significantly reduce the effectiveness of protections on important sites of high historic, natural, wildlife or amenity value.

Furthermore, the estate rests within a Conservation Area and the seven buildings are all grade-A listed. As such, any decision the CEC makes concerning the estate is by definition of significant importance to the people of the city and Scotland at large. Finally, the significance of the estate in terms of architectural, historical, natural heritage and wildlife considerations impose a very onerous duty upon the CEC to uphold the highest levels of probity and propriety in their decision making. If that does not happen then it would create a loss of confidence and fundamental breach of trust between the people of Edinburgh and the CEC.

Therefore, the FoC do have legitimate interest and standing to challenge any decision the CEC make concerning the estate that we perceive as erroneous in law, not reasonably arrived at on the facts, perverse or biased, contrary to natural justice or ultra vires in nature.

[1] – The Friends of Craighouse has collected paper signatures from over 5,000 people; have pledges from a number of politicians; have represented the community in an official capacity at the Community Liaison Forum; have engaged with the community councils and relevant heritage bodies; and have a large active membership. The Friends of Craighouse are the only substantive community group dedicated to protecting the landscape and historic buildings at the Craighouse estate.

Heads of Complaint

A. Development not started as pursuant to s27 of the Town and Country Planning (Scotland) Act 1997.

The CP through their agents ME claim they started development and that consent 01/04599/FUL is now active1. In that correspondence with the CEC, they claim that they dug a trench on the 22nd of June 2012 within the area that is delineated in the 01/04599/FUL plans as a car park. This is the only claim that the CP make in relation to beginning development. Therefore, if this specific item is not a lawful beginning to development, the consent must have lapsed.

The position of the FoC is that development did not begin, hence the consent lapsed.

1. There was no material operation as per s27(4) so the consent was not activated

ME state in their letter “a trench was excavated within the area of the ‘approved’ car park”. It goes on to say,

Whilst the area of excavation works undertaken related to the construction of the foundations to the ‘approved’ car park, the trench was back-filled on the same day… The trench was back-filled and made good for Health and Safety reasons, as this part of the site remains open to members of the public.”

s58(1) of the Town and Country Planning (Scotland) Act 1997 defines the time period within which development must start in relation to a specific planning consent,

58 General condition limiting duration of planning permission

(1) Subject to the provisions of this section, every planning permission granted or deemed to be granted shall be granted or, as the case may be, be deemed to be granted subject to the condition that the development to which it relates must be begun not later than the expiration of—

(a) 5 years beginning with the date on which the permission is granted or, as the case may be, deemed to be granted, or

(b) such other period (whether longer or shorter) beginning with that date as the authority concerned with the terms of the planning permission may direct.

The date on which a development is considered to have begun is defined in s27,

27 Time when development begun.

(1) Subject to the following provisions of this section, for the purposes of this Act development of land shall be taken to be initiated—

(a) if the development consists of the carrying out of operations, at the time when those operations are begun;

(b) if the development consists of a change in use, at the time when the new use is instituted;

(c) if the development consists both of the carrying out of operations and of a change in use, at the earlier of the times mentioned in paragraphs (a) and (b).

(2) For the purposes of the provisions of this Part mentioned in subsection (3) development shall be taken to be begun on the earliest date on which any material operation comprised in the development begins to be carried out.

(3) The provisions referred to in subsection (2) are sections 52(2), 53(6), 54(4), 58, 59 and 61.”

It can be observed that the date the development begins is the earliest of either carrying out operations or a change of use, both by means of a “material operation”. s27 goes on to clarify the meaning of material operation.

(4) In subsection (2) ‘material operation’ means—

(a) any work of construction in the course of the erection of a building,

(b) any work of demolition of a building,

(c) the digging of a trench which is to contain the foundations, or part of the foundations, of a building,

(d) the laying of any underground main or pipe to the foundations, or part of the foundations, of a building or to any such trench as is mentioned in paragraph (c),

(e) any operation in the course of laying out or constructing a road or part of a road, or

(f) any change in the use of any land which constitutes material development.

(5) In subsection (4)(f) “material development” means any development other than—

(a) development for which planning permission is granted by a general development order for the time being in force and which is carried out so as to comply with any condition or limitation subject to which planning permission is so granted,

(b) development of a class specified in paragraph 1 or 2 of Schedule 11, and

(c) development of any class prescribed for the purposes of this subsection.”

It is clear that the developer must undertake at least one material operation as defined in s27(4) to meet the requirements for either a beginning by “carrying out of operations” or “change in use” pursuant to s27(1). If the developer does not undertake a material operation before the expiry of the consent then it cannot have been properly activated. This is the contention of FoC in relation to 01/04599/FUL.

Each item in s27(4) shall be dealt with in turn.

i. “(a) any work of construction in the course of the erection of a building”

There are three limbs here: was there any “construction”, if so whether it was “in the course of the erection of a building” and whether indeed the car park comprises a “building”. To satisfy the criteria for this material operation, any work would have to meet all three limbs.

Construction”

Unfortunately, the Act does not define “construction”. There is also a paucity of authorities on the matter with, seemingly, the only relevant authority being Ceredigion County Council v. National Assembly for Wales and Mr E.D. Harrison [2001] EWHC Admin 694. Although Ceredigion concerns English law, the wording is precisely the same as s27(4)(a), so it is arguably instructive. At 19. Richards J opines,

19. ‘Construction’ is not defined in section 290(1) or elsewhere in the 1971 Act. I see no reason for giving it anything other than its ordinary English meaning. There is nothing to show that it is intended to bear any special or extended meaning. It is not to be equated with “erection” as defined in section 290(1): the very fact that section 43(2)(a) refers both to “work of construction” and to “in the course of erection” is a strong indication that the concepts are not the same. The words “any work of construction” in (a) may also be contrasted with the language used in the rest of section 43(2), for example the expression “any operation in the course of laying out or constructing a road” in (d). The use of that expression in (d) highlights the fact that the draftsman has chosen a the specific concept of “construction” in (a).”

Certainly in this case, the sole act of digging a single trench with no purpose and immediately back-filling it could not be properly considered construction. Furthermore, s27(4)(c) of the Act specifically mentions digging of a trench, so one can presume if the drafter of the legislation had the mind to create a specific material operation for that action then the mere digging of a trench with no other construction works cannot be considered to fall within the auspices of s27(4)(a).

Finally, the Oxford English Dictionary definition of “construction” states,

The action of framing, devising or forming, by the putting together of parts; erection, building”

So even the commonly accepted meaning does not lend any credence to the idea that a single trench could be “construction”: there were no “parts” and there was no erection of any building, which strongly suggests digging a trench is not the construction of a building.

in the course of the erection of a building”

In any instance, the first limb of “construction” is qualified by the second limb, “in the course of the erection of a building”. Well, it can be plainly seen that the trench was not dug in the course of the erection of a building: there was nothing erected, certainly no building.

building”

Finally, the term “building” must be considered. “building” is defined in the Act, in s277,

‘building’ includes any structure or erection, and any part of a building, as so defined, but does not include plant or machinery comprised in a building; ”

There is authority concerning this definition however it is not particularly instructive in this instance, being restricted to structures such as cranes, gazebos, and scaffolding.

In a common sense approach, it cannot be said that a car park, hard standing or hard surface is a structure. Similarly, it is clearly not an erection and certainly not what would commonly be accepted as any part of a building.

In any case, if it were so that a hard standing were a building, one would have to admit things like landscaping and paths into the definition of a “building”, which would be a highly undesirable result and contrary to existing law.

Some small additional guidance can be found in The Town and Country Planning (General Permitted Development) (Scotland) Order 1992,

4.—(1) The provision within the curtilage of a dwellinghouse of a hard surface for any purpose incidental to the enjoyment of the dwellinghouse.

(2) Development is not permitted by this class within a conservation area or within the curtilage of a listed building.

in comparison with,

5.—(1) The erection or provision within the curtilage of a dwellinghouse of a container for the storage of oil. ”

or,

6.—(1) The installation, alteration or replacement of a satellite antenna on a dwellinghouse or within the curtilage of a dwellinghouse. ”

It can be seen that the verbs used in each instance change and that for a hard surface, the verb “provision” is used, not “construction” nor “erection”.

any work of construction in the course of the erection of a building

As can be seen from above, none of the three limbs in the s27(4)(a) definition were met, therefore this cannot be a material operation for the purposes of 01/04599/FUL.

ii. “(b) any work of demolition of a building”

This item is easily disposed of: there was no building to demolish, so it cannot possibly apply and cannot be a material operation for the purposes of 01/04599/FUL.

iii. “(c) the digging of a trench which is to contain the foundations, or part of the foundations, of a building

While there was apparently a trench dug, it was not to contain the foundations, in whole nor in part, of any building. The trench was immediately back-filled, it contains the same soil and rock that was removed from it, therefore does not contain the foundations of a building. The developer did not take any materials, machinery, tools nor workmen to be able to place foundations within such a trench on the 22nd of June 2012. In other words, at the time of digging the trench on the 22nd June 2012, the trench was not to contain the foundations of any building or part thereof. Finally, whatever happens in the future, the trench will never contain the foundations of a building because the trench was immediately filled in and no longer exists.

Furthermore, there would be no “building” at that space: as described above, the car park would not comprise a “building” in relation to the Act.

So this item can also be disposed of: the trench absolutely could not have contained the foundations or part of the foundations of a building; as such it fails to be a material operation for the purposes of 01/04599/FUL.

iv. “(d) the laying of any underground main or pipe to the foundations, or part of the foundations, of a building or to any such trench as is mentioned in paragraph (c)”

There were no pipes or underground mains laid, therefore this item cannot apply and does not constitute a material operation for the purposes of 01/04599/FUL.

v. “(e) any operation in the course of laying out or constructing a road or part of a road”

This item has two limbs, “any operation in the course of laying out or constructing” and then “road or part of a road”. Each limb will be treated separately.

any operation in the course of laying out or constructing”

The wording is rather precise: “in the course of”. That requires that the work is actually contained within the realm of laying out of constructing a road and that it is not for some other purpose or indeed without a purpose.

Digging a trench and immediately filling it back in, does not fall into the “course of laying out or constructing”. It achieved nothing and marked-out nothing.

If any doubt remained over this item, in the letter ME sent to the CEC on the 29th June 2012, it states,

Whilst the area of excavation works undertaken related to the construction of the foundations to the ‘approved’ car park, the trench was back-filled on the same day…”

So by ME’s own admission, the work was not in “the course of laying out or constructing a road”. Therefore, by this point alone, s27(4)(e) cannot be a material operation for the purposes of 01/04599/FUL.

The second limb of this test will however still be looked to for the purposes of completeness.

road or part of a road”

To be construed as an operation in the course of laying out or constructing a road or part of a road, there must be a road to be constructed either at the point where the claimed works took place or within that locus. The precise meaning of “road” must resultantly be known.

The definition of a road is set out in statute, specifically s151 of the Roads (Scotland) Act 1984,

‘road’ means, subject to subsection (3) below, any way (other than a waterway) over which there is a public right of passage (by whatever means and whether subject to a toll or not) and includes the road’s verge, and any bridge (whether permanent or temporary) over which, or tunnel through which, the road passes; and any reference to a road includes a part thereof”

The above definition is imported by section 192(1) of the Road Traffic Act 1988, which has extent to Scotland, however has been the subject of certain amendments in terms of paragraph 78 of Schedule 4 to the Road Traffic Act 1991. Given the Road Traffic Act 1998 and 1991 are primarily for the regulation of road traffic whereas the Roads (Scotland) Act 1984 is for the making of provisions as regards roads in general, the latter and slightly more restrictive definition is appropriate for these purposes.

There is some authority in Scotland to give guidance on what should be considered a road and what should not. The English definition is also broadly similar, so authority from England is at least instructive.

For the area where the trench was dug, the plans for 01/04599/FUL clearly show it as being within the boundaries of the car park. In more common parlance, the car park is a hard-standing or hard-surface; the more important question here is whether the approved plans in 01/04599/FUL create a road, or merely a hard-standing.

Dealing with the first question: is the car park a “way”. Looking at the plans, one can clearly see the west, north and east boundaries of the car park are fenced off with 90cm high posts and wire fencing; on the north side there is to be Ivy grown and the west and east sides, Common Beach. These would considered impassible in the normal course of matters, so the car park cannot be considered a way – it leads nowhere. There is no transit from one place to another.

The second question is that there must be a public right of passage. On the basis of the plans as consented there is no and cannot be any right of passage through the car park. Moreover, all existing authority to date has focused on assessing situations concerning car parks that were in existence before the relevant incident took place. In this situation, the car park is not in existence so there cannot be a right of passage through it as it does not yet exist.

If we look to Clark (A.P.) and Others v. Kato, Smith and General Accident Fire & Life Assurance Corporation PLC, Cutter v. Eagle Star Insurance Company, UKHL 1998 for guidance, Lord Clyde cautions against an unnatural approach,

In the present case the question is raised whether one or other or both of the car parks qualifies as a road. In the generality of the matter it seems to me that in the ordinary use of language a car park does not so qualify. In character and more especially in function they are distinct. It is of course possible to park on a road, but that does not mean that the road is a car park. Correspondingly one can drive from one point to another over a car park, but that does not mean that the route which has been taken is a road. It is here that the distinction in function between road and car park is of importance. The proper function of a road is to enable movement along it to a destination. Incidentally a vehicle on it may be stationary. One can use a road for parking. The proper function of a car park is to enable vehicles to stand and wait. A car may be driven across it; but that is only incidental to the principal function of parking. A hard shoulder may be seen to form part of a road. A more delicate question could arise with regard to a lay-by, but where it is designed to serve only as a temporary stopping place incidental to the function of the road it may well be correct to treat it as part of the road. While I would accept that circumstances can occur where an area of land which can be reasonably described as a car park could qualify as a road for the purposes of the legislation I consider that such circumstances would be somewhat exceptional.”

It may be perfectly proper to adopt even a strained construction to enable the object and purpose of legislation to be fulfilled. But it cannot be taken to the length of applying unnatural meanings to familiar words or of so stretching the language that its former shape is transformed into something which is not only significantly different but has a name of its own. This must particularly be so where the language has no evident ambiguity or uncertainty about it. While I have recognised that there could be some exceptional cases where what can reasonably be described as a car park may also qualify as a road, it is the unusual character of such cases which would justify such a result in the application of the statutory language rather than any distortion of the language itself.”

Although the conclusion on the facts were different in this particular case the same general principals were confirmed in Kirsty Aird v. Procurator Fiscal, Glasgow1998. The question in Airdconcerned whether the forecourt of the then Strathclyde Regional Council offices comprised a road. The forecourt was used by pedestrians as a short-cut between multiple locations, so in that case functioned as a way. It is confirmed however, if it was wholly a private car park as is delineated in 01/04599/FUL then there would be no problem with immediate disposal as not comprising a road.

So the position was that there was access at certain times to the forecourt by drivers of cars generally while at other times access was confined to permit holders. In addition the magistrate found that there were a number of entrances and exits to and from the car park area which were capable of being, and were, used by pedestrians as shortcuts between Holland Street and a neighbouring street, Elmbank Street, and as an access to Charing Cross Railway Station.”

We agree that a “way” is an area in which some form of travel takes place. This is plain from study of the definitions of the word in the Shorter Oxford Dictionary. Whether such an area is or is not a way is essentially a question of fact. (Clarke v. Kato 1998 1 W.L.R. 1647 per Lord Clyde at 1653). So understood, a private car park which is strictly confined to use by persons authorised to bring their cars there in order to leave them would not be regarded as a way. If that had been found to be the situation in this case we would have had no difficulty in holding that the forecourt was not a road within the statutory meaning. But the facts are otherwise.”

We therefore come back to the facts of the case to see whether the forecourt can be described as a way to which the public has access. As we have noted the forecourt was used by local authority employees for restricted car parking during certain periods. There was also unrestricted use of the area at other times and for extended periods for drivers to come in and leave their cars and proceed elsewhere. Finally pedestrians used the locus, apparently at all times, as a means of progressing from one part of the town to another.”

A similar albeit far less instructive finding is detailed in John Horn v Procurator Fiscal, Kirkcaldy 1998, whereby their Lordships decided the Sheriff deciding the originating case was not entitled to come to the conclusion that the car park comprised a road,

There is no finding that members of the public in general had access to the car park in the sense that they normally resorted to it and might be expected to be there. In our opinion on the basis of the findings made by the sheriff in this case, she was not entitled to infer that the car park was a way to which the public had access. That being so it follows that it was not established that the car park fell within the statutory definition of ‘road’.”

There is no presumption that a car park or hard-standing comprises a road unless exceptional circumstances dictate it must be so. These circumstances must be decided on the facts of the case. In the situation of the car park as delineated in 01/04599/FUL, it certainly cannot be so: there is and cannot be any way as the borders of the car park would prohibit it; there is no general right of passage as the car park does not yet exist and in any case could not be used as such.

The only conclusion remaining is that the car park could not possibly comprise a road. Therefore, any works carried out in that region cannot be for the constructing or laying out of a road.

Therefore, again, s27(4)(e) cannot be a material operation as regards 01/04599/FUL.

vi. “(f) any change in the use of any land which constitutes material development”

The only activity that was undertaken on or before the 25th June 2012 did not change anything in the function or nature of the land. For years it has been covered in undergrowth, trees, bushes, etc and today, it still is in that condition. It is certainly not possible to park a car there.

The area was designated as the “contractor’s car-park” in a consultation document from CP2, however it does not appear to have been used as a car-park for a considerable period of time. Also, in a document obtained under Freedom of Information from CEC, under the heading “PLANNING ADVICE (24 August 2010) the area is described as: “Site north of car park: Currently an area of hard standing well-screened from original entrance road”.

As an esto argument, using the area as a car-park, when it is already labelled a car-park and has been used as a car-park in the past cannot be considered a change of use. Interestingly, no attempt was made to park a car there as part of the attempted activation of this consent.

There has been no change of use, hence s27(4)(f) cannot be a material operation for the purposes of 01/04599/FUL.

Items i. through vi. show there was no material operation on or before the 25th June 2012. Therefore, development had not begun and the consent has lapsed.

B. No lawful start within the realm of the planning consent.

To active the consent, the CP would have to have undertaken a lawful start. This requires that all the suspensive conditions are discharged, that the work undertaken is pursuant to the planning consent and furthermore that any lawful start cannot be de minimis in nature.

In East Dunbartonshire Council v Secretary of State for Scotland 1998, there is considerable discussion on the issue of intent and indeed what construes a minimum operation. In his summing-up Lord Coulsfield opines,

It seems to us however that the solution to that problem, if it is a problem, is more likely to be found by applying an objective approach and considering firstly, whether what has been done has been done in accordance with the relevant planning permission and, secondly, whether it is material, in the sense of not being de minimis. It may be that that is what Eveleigh L.J. had in mind in using the word “colourable” in the passage quoted above. On that approach, the question would be one of fact and degree, as was indicated in the High Peak case.”

There are other authorities to support these propositions but shall be omitted for the purposes of brevity. Suffice to say that to be a lawful start, the claimed operation must be material, pursuant to the planning consent and not de minimis, the degree of which to be judged on the facts of the case.

1. The work was not pursuant to the planning consent so cannot be a lawful start

The area where the trench was dug is marked in the plans as a car park. So, it stands to good reason that if one is going to construct a car park, the operations involved must be for that purpose. In objective assessment, digging a trench then immediately filling it in again is not involved in constructing a car park. None of the correspondence from ME to CEC specifies properly the purpose or character of the trench in question, if anything it is decidedly vague in that respect, so it cannot be seen to be for constructing the car park. It could quite easily have been for a completely different activity entirely unrelated to 01/04599/FUL.

This assessment is further supported on the facts in that there were no attempts to comply with the written scheme of investigation as prescribed by the suspensive archaeological condition nor were there any attempts to comply with the provisions as concerns tree protection, again a suspensive condition.

The presumption must be that the trench was not pursuant to 01/04599/FUL and that it therefore was not a lawful start.

2. The work was de minimis therefore not a lawful start

The character of the work in digging the trench is clearly de minimis: on an objective assessment any reasonable person would discern that it was not a material operation in the construction of anything – the area in question is in precisely the same condition as it was for the preceding five years the applicant held the consent for. Their work accomplished nothing, prepared for nothing and indeed did nothing. It had no material impact.

Similar digging and back-filling work has since been performed all around the Craighouse site, including areas well outwith the delinated areas for 01/04599/FUL – as part of site investigations for their future plans. No planning consent was applied for or deemed necessary for these other digging and back-filling operations.

This is a clear example of a developer attempting to retain permission with no intention of undertaking the development by doing a token de minimis gesture.

C. Failure to properly discharge all suspensive conditions before commencing work.

The 01/04599/FUL final consent detailed several suspensive conditions, specifically conditions 4, 8, 10, 12 and 16. These conditions were not fully discharged before the claimed works were carried out, hence no lawful start occurred and 01/04599/FUL lapsed.

Many of the conditions specify that plans or further documentation be provided to the CEC. Some conditions also require that the developer undertake certain activities on-site or follow their plans before development can commence. It shall be shown below that in several instances, this did not happen.

Each of the suspensive conditions were obviously not specified frivolously: they were drafted well after the applicable 1998 Scottish Government Circular and there is more than sufficient specification to support their necessity. On inspection, it can be seen that the exceptions detailed in Whitley do not apply either. Therefore, any breach of a suspensive condition does go right to the heart of the consent and is not a lawful start.

1. Condition no. 4 – Archaeology

The text of condition 4 is as follows,

No development shall take place within the campus until the applicant has secured the implementation of a programme of archaeological work, in accordance with a written scheme of investigation which has been submitted to and approved in writing by the Head of Planning & Strategy, having first been agreed by the City Archaeologist.”

Clearly this is a suspensive condition. It requires that the developer have a written scheme of investigation approved by the Head of Planning & Strategy and also the City Archaeologist; it also requires that the developer secure the implementation thereof.

Turning first to the written scheme of investigation. In the bundle relating to discharge of conditions on the CEC portal, there is an email from a “FreeServe” account dated 11th June 2012 putatively from John Lawson, City Archaeologist, concerning the archaeological condition for 01/04599/FUL. The contents of the short email are repeated below,

Ive had a look over the WSI prepared by Wardell Armstrong in relation to the archaeological condition atteched to app 01/00599/FU1 and find it acceptable. As is normal practice the should not be formally discharged until the work has been undertaken but i’m happy for work/developmentb to start on site.”

In trying to read through the numerous errors, the wording seems to imply that the suspensive condition should not be discharged. If the contrary position is adopted – that one cannot discern as much – then the default position must be assumed that he did not advise discharge, so the result is the same. He goes on to say that he is happy for work to commence on site, thankfully his role is advisory in nature and he was not the decision maker.

From what can be surmised the written scheme of investigation has not been approved in writing by the Head of Planning & Strategy.

In short summation, it was advised that the condition not be discharged at that point. At best one can say there was tacit approval of the written scheme of investigation.

Looking back to the wording of the suspensive condition, it says that no development can take place before the application has secured the implementation of the written scheme of investigation. The requirements of the written scheme of investigation are onerous. For example, item 4.2. requires that sixteen trial trenches of dimension 1.8m x 30m be dug prior to the evaluation commencing. Obviously, this has not happened.

One can immediately see that this suspensive condition was not discharged, therefore there was no lawful start and the consent lapsed.

There is a corollary in that if it is pleaded that the trench dug on the 22nd June 2012 was for archaeological works then it can immediately be discounted as a material operation for the purposes of s27(4).

2. Condition no. 8 – Tree Protection

The text of condition no. 8 is as follows,

Drawings showing measures to protect trees during construction are to be submitted and approved by Head of Planning and Strategy prior to incorporation in the contract with the builder and to be implemented before work is commenced on site. The drawings are to show:

  • the construction and method statement of any development including, service trenches, roads, paths and car park areas and associated earthworks in the vicinity of mature trees.

  • the alignment and specification of fences to protect trees during construction.

  • the location of contractors’ compounds and access arrangements.

  • the location of temporary spoil heaps and haul roads.”

Now, this condition is more stringent than condition no. 4, not least because it requires that the relevant drawings are to be approved by the Head of Planning and Strategyand incorporated in the contracts with the builders.

Discounting whether the drawings were approved by the Head of Planning and Strategy, the CEC did not make a formal notice discharging suspensive conditions until the 14th June 2012. That means the CP would have to engage with builders between the 14th June 2012 and 22nd June 2012 and have the contract agreed in that time-frame. If the builders were engaged earlier, the drawings were unapproved; if they engaged later then the drawing cannot have formed part of their contract. Therefore, there were all of six days to create such a contract. The FoC would like confirmation in writing that this was indeed done, as to discharge the condition the CEC would have to have seen proof of such.

Again, the most important part of this suspensive condition is that is must be implemented before work may commence. The method statement as required by the condition sets out a mandatory order of works as described in Part 3 copied below,

It is critical that protective measures, tree works and construction are undertaken in the correct order to ensure the long term viability of the existing tree resources. This section sets out the order in which works should be undertaken.

  1. All tree works, including facilitative work

  2. Erection of protective fencing

  3. Site clearance

  4. Construction

  5. Landscaping outwith Construction Exclusion Zone (CEZ) (hard landscaping, earthworks)

  6. Removal of protective fencing

  7. Landscaping within CEZ (planting, seeding, mulching)”

Before the claimed works on 22nd June 2012, there was no erection of protection fencing and certainly not to the specification in the relevant drawings. Furthermore the site was not cleared and one can assume the facilitative work was also not done. As such, any construction would not have been in accordance with the approved plans and therefore do not constitute a lawful start. Resulting, the consent must have lapsed.

3. Condition relating to other consents (marked as 18. on second list)

There is one final condition that is worded in the manner of a suspensive condition, albeit listed in the column for reasons on the original conditions. It reads,

18. NB This consent is for planning permission only. Work must not begin until other necessary consents, eg listed building consent, have been obtained.”

It should be noted that the listed buildings consent expired in May 2007. Given the wording is of a suspensive condition, even by the most lax construction, it specifically prohibits work starting until the listed building consent is in place. Therefore, the work was not a lawful start and the consent lapsed.

D. The CEC issued a notice discharging the suspensive conditions that was not competent.

As detailed above, at least three of the suspensive conditions were not properly discharged. Despite this, a notice was sent on the 14th June 2012 stating as much. In light of this, the notice was not competent. The CEC knew this to be so as early as July 2012 as the FoC informed the CEC of the same, yet the CEC took no action to rectify the situation.

Henry Boot Homes Limited v Bassetlaw District Council [2002] EWCA Civ 983 is instructive in this instance. It covers a very similar situation of a council accepting that work had started on a consented development, despite suspensive conditions not being implemented. This was challenged by a third party, which the council then accepted was a valid challenge and changed its view on the initiation of development.

Paragraph 52 states:

Even more than many areas of public law which concern an individual and a public body, planning law is likely to have to reflect the fact that third parties and the public generally may have interests in any decision. I agree with what was said by Sullivan J in the present case at para 140:

… It is important at all times to remember the public nature of Town and Country Planning. It is not a matter for private agreement between developers and Local Planning Authorities.’”

This highlights the issue in relation to 01/04599/FUL: that it is not a private agreement between the developer and the council, where the council can choose not to require suspensive conditions to be implemented. The judgement in Henry Boot Homes goes on to suggest that if the developer wants to take on a development in a phased manner, whereby not all conditions are fully implemented, there is a statutory process to do so. The developer can apply for modification to the conditions to allow a phased development to go ahead, that statutory process describes how such a decision can be made and allows for public interest and public oversight to be taken into account.

The developer cannot have any legitimate expectation that it can take on the development in a phased manner, not implement the suspensive conditions or not go through the statutory process simply because it is running out of time on the planning consent. Notably, at the point of June 2012, it was more than ten years from the date of application so there is no excuse for mora in relation to implementing 01/04599/FUL.

Paragraph 54 of Henry Boot Homes supports this proposition:

The scope, therefore, for waiver by non-statutory means of the need to comply with a condition must be extremely limited.”

Paragraph 55 continues:

One of the reasons is that it is difficult to see how a legitimate expectation, said to derive from the conduct of the local authority, could operate so as to prevent an interested third party from questioning whether development has validly begun and whether the planning permission is still extant”

This judgement gives legal backing to FoC’s view that the council had no legal authority to issue a notice discharging the suspensive conditions.

Furthermore, the CP can have no legitimate expectation that it could keep the planning permission if it had not implemented those suspensive conditions.

Therefore, the clear course for the CEC is to reject its previous notice that work had started and instead state that the consent has lapsed and affirm that the developer in this instance has no recourse.

E. The original consent notice is not competent.

The original 01/04599/FUL and 01/04599/LBC applications were lodged in 2001 with the Development Quality Sub-Committee assessing them jointly and recommending conditional granting of both on the 15th May 2002. The 01/04599/LBC was granted on 24th May 2002 while the 01/04599/FUL consent was not granted until 26th June 2007, by which time the LBC had expired.

The planning consent and Listed Building Consent were applied for jointly because the buildings (both the Grade A Listed buildings, and the new building) were to be joined together under ground.

1. The 01/04599/FUL consent notice is not competent because it involves changes to a listed building for which listed building consent had lapsed

1a. The 01/04599/FUL consent as issued could not be implemented without the listed buildings consent due to a condition explicitly specifying as such

To complete the 01/04599/FUL consent, the listed buildings consent is required. To undertake such work to a listed building without consent is a criminal offence. Without the listed building consent, the 01/04599/FUL consent obviously could not be completed and there is no reason to believe that listed buildings consent would be granted retrospectively, cf. Scottish Planing Policy 1 (SPP1), paragraph 57. When granted in June 2007, the 01/04599/FUL consent did not have any prospect of completion and is therefore not competent.

The actual 01/04599/FUL permission as issued in June 2007 states explicitly that “Work must not begin until other necessary consents, eg listed building consent, have been obtained”. Clearly the listed building consent had already expired, so the 01/04599/FUL consent could not be implemented without the applicant returning to obtain listed building consent. So in fact, the planning consent was never implementable.

2. The consent notice is not competent because officials acted without elected approval

The first line of the proposed consent document that the Development Quality Sub-Committee approved states:

The development hereby permitted shall be commenced no later than five years from the date of this consent”.

The joint application they were voting on was two consents: the listed building consent was granted 24th May 2002, while the planning consent was granted more than 5 years later on 26th June 2007. This meant that officials were allowing work to start more than ten years after the meeting of the Development Quality Sub-Committee. This cannot have been their understanding or intention at the time. Officials were not acting within a reasonable understanding of the information put before the Development Quality Sub-Committee in 2002 and should have returned to the committee for approval in 2007.

3. The 01/04599/FUL consent notice is not competent because there were several material changes between the date that the Development Quality Sub-Committee decided upon the issue and granting of permission

In 2006, Napier University produced a new Estates Strategy in which it is decided to sell Craighouse and not proceed with the building and associated car-park. The original recommendation to the Development Quality Sub-Committee states “Given the logistics of the site, and the requirements of the university, a departure from policy is considered acceptable in this case”. So, the requirements of the university are a key material impact on the decision to grant consent and had changed between the point that the Development Quality Sub-Committee made its decision and granting of consent.

4. The 01/04599/FUL consent notice is not competent because there was an undue delay between the Development Quality Sub-Committee deciding upon the issue and granting of permission

The Development Quality Sub-Committee decided upon the issue on the 15th May 2002, yet the 01/04599/FUL consent was not granted until 26th June 2007, more than five years afterwards.

F. The CEC failed to properly undertake their statutory duties.

1. The CEC took a laissez-faire approach to discharge of the suspensive conditions

In correspondence between FoC and the CEC, it is clear that the planning officials responsible were unaware of the nature and location of the works. For example, in a letter to FoC dated 12th July 2012, David Leslie states,

If works were taking place which could impact on the trees then this condition would be relevant. However, given the nature, scale and location of the works that have taken place, there are no concerns relating to the trees.”

Given that the works involved digging in woodland, this statement seems strange. Irrespective of that, if the planners considered that development was commencing the conditions were, and are, of the utmost importance and cannot be blithely ignored.

In the same letter, David Leslie continues:

However, given the nature of the consent and Craighouse Partnership’s current aspirations for the site, there is considerable doubt as to whether the arts facility will be progressed further”

The FoC consider that to be an expression of sentiment from CEC that they need not consider the suspensive conditions because the CEC does not expect the development to continue. Aside from the erroneous nature of such a stance, surely if the CEC presumed the development were not proceeding then it would have confirmed that the consent lapsed.

2. The CEC did not make available full and proper information concerning 01/04599/FUL to the public as required

This section of the complaint is about a process that occurred over five years ago. There was no opportunity at the proper time for members of the public to challenge this process as public information was not available.

On 4th August 2006, planning officials delivered an extensive list of planning consents and applications at the Craighouse site as part of a report to recommend to grant permission to Napier to erect a memorial in the grounds at Craighouse. However, despite this extensive list, 01/04599/FUL nor 01/04599/LBC were not included. Therefore, by 2006, it had become extremely difficult to obtain information about this planning consent.

FoC visited the planning archives several times during 2011 and 2012, as well as emailing questions to the CEC and telephoning. The FoC only obtained the planning consent decision notice itself after visiting on 5th July 2012 and numerous protracted discussions. On all previous visits and after all previous requests they had obtained no copy of the decision notice was forthcoming, despite this being documentation that should be readily available toe the public. FoC did obtain a signed but undated and incomplete copy of the Section 75 agreement in 2011. This version was released on the CEC planning portal on 1st October 2012, described as “copy of legal agreement”. Only after many visits, requests to multiple departments, and complaints to councillors, did they finally obtain a correct, dated and fully-executed copy of the Section 75 agreement.

Because the information that should have been made available publicly was not available earlier, there was no opportunity for anyone to complain earlier. So any complaint by the public as concerns the consent is not in mora but instead now at the earliest possible opportunity. This is the earliest opportunity that this planning consent can be challenged by members of the public and it is being so challenged.

3. The CEC failed on the material before them to adopt the correct approach of determining whether the consent was activated

The CEC did not adopt the correct approach when assessing whether the consent had been activated. The correct approach would have been,

i) ensure that the 01/04599/FUL consent was in a condition that it could be activated, in other words that the other consents it depended on were in place;

ii) determine whether all the suspensive conditions had been fully discharged;

iii) whether the claimed work was more than de minimis and pursuant to the 01/04599/FUL consent; and,

iv) whether the claimed work was indeed a material operation as regards s27(4) of the Act.

In relation to i., the CEC failed to determine whether 01/04599/LBC had expired or was required, as it is patently so.

In relation to ii., the CEC only appraised the documents sent by ME, not whether the suspensive conditions had actually been discharged. In fact, the suspensive conditions had not been discharged and the CEC took a particularly lax approach.

In relation to iii., there seems to be no assessment of this.

In relation to iv., there seems to have been no formal assessment of this.

For all four stages, the CEC either completely failed or did not sufficiently assess the situation.

The CEC’s confirmation to ME that the consent had been activated was therefore a decision that erred in law, was not reasonably arrived at on the facts, arguably negligent and made ultra vires.

Finally, the decision to notify ME that it accepts work started could be potentially be viewed as a biased decision as the CEC stands to gain financially through the s75 agreement.

1 Letter dated 29th June 2012 to Mark Turley, CEC, ref: ADM/SV9335/18

2 “Consultation-Boards-Final-rfs.pdf” from CP available on their website, but shown to the public in March 2012

Posted in Uncategorized | 1 Comment

Time-Line for the Arts Faculty Building Consent and Section 75

Timeline for planning application 01/04599/FUL

In June 2012 The Craighouse Partnership claimed to have activated a decade-old consent for this 80,000 sq ft university building by digging a “trench” and filling it in again. The Council waived associated pre-conditions that would have protected the site. The Craighouse Partnership are now applying to change the conditions further so as to delay, maybe indefinitely, having to pay the associated costs to the Council to the tune of £180,000.

We met with the Council planners last week who confirmed that this consent would allow removal of mature woodland, the putting in of carparking and infrastructure – in short the site could be left in a mess without any obligation to build the associated institutional building. Although this could also be built. This consent would last in perpetuity.

The Friends of Craighouse are preparing a formal complaint to the Council. We are also unhappy about the lack of transparency and unavailability of paperwork that should have been in the public archives.

Background

  • Napier University purchased the Craighouse site in 1994.
  • Around £14 million of public funds were granted to Napier to carry out refurbishment of the existing buildings between 1994 -1996, and Napier fully moved onto the site in 1996.
  • In 2001, as part of their then Estates Strategy, Napier applied for planning permission to develop a new Arts Facility Building at Craighouse. Although controversial, planning permission was provisionally granted in May 2002 because it was a planning application by a university to specifically develop university facilities.

However, as the timeline below shows, in subsequent changes to their Estates Strategy from 2006, Napier decided to abandon their development plans for Craighouse. Instead, they decided to redevelop their Sighthill Campus. However, in conjunction with the Council, Napier pressed on with securing planning permission for Craighouse – planning permission they knew they would never use !

Any attempt by speculative developers ( incl Napier themselves ) to use this planning permission for residential development would be entirely inappropriate.

Here is a timeline we have put together from our understanding to explain what has happened. We would be happy to hear from anyone in relation to this.

KEY DATES

20 December 2001 –Planning application received and validated by City Of Edinburgh Council  (Thursday just before Christmas holidays)

15 May 2002 – Development Quality Sub-Committee grant conditional planning permission subject to a Section 75 Legal Agreement.

4 August 2006 – 01/04599 not included amongst other applications in report from Planning officials to the Planning Committee. This was a report to recommend to grant  permission to Napier to erect a memorial in the grounds at Craighouse. They give a long list of prior planning applications and consents, but miss out 01/04599/FUL.

2006  Napier Estates strategy outlines intention to dispose of Craighouse campus

26 Mar 2007 – Napier appoint architects to design a new Sighthill Campus

14 May 2007  –  Section 75 Legal Agreement signed by Napier University 5 years after the Planning Committee met

23 May 2007 –   Listed Building Consent 01/04599/LBC expires. (Without this consent, the project cannot be completed in line with the original plans and the planning consent stated that work could not start until other consents – such as LBC – obtained)

6 June 2007   –  Section 75 Legal Agreement signed by Council, despite Napier not being able to complete  the project due to the expiry of the Listed Building Consent, and Napier’s new strategy to sell the site – both material changes. Officials do not refer this decision back to the planning committee. Over 5 years after the Planning Committee met.

25 June 2007  –  Section 75 agreement lodged at Registers Of Scotland

26 June 2007  –  Planning Dept issue Final Decision Notice  granting planning permission for 01/04599/FUL (over 5 years on from that decision by the planning committee in 2002). Development to be commenced no later than 5 years from this date.

25 Mar 2011 – Napier announce the sale of Craighouse has taken place

During 2011, and 2012, the Friends make a series of visits to the planning archive to see the Section 75 and planning consent. We find an incomplete Section 75, and no planning consent. We also make a series of Freedom of Information Requests to Napier for paperwork connected to this consent – they say they have no files.

8 June 2012 – Montagu Evans ( developers’ agent)  submits a set of plans to  Planning Dept to protect the site during work, as required by the original consent. This includes a tree  protection plan, landscape management plan, and a scheme of investigation for  archaeological evaluation.

14 June 2012 – Planning Dept. write to Montagu Evans ( developers’ agent ) accepting the submitted  plans, and as a result, discharge a number of the conditions to protect the site  included in the planning consent.

21 June 2012   Montagu Evans write to Planning Dept. submitting an Application For Modification Of   Planning Obligations. This is an application to delay, perhaps indefinitely, the payments they are required to  make by the Section 75 Legal Agreement concluded in June 2007 that amount to £180,000. The public copy of the application includes a copy of the Section 75 agreement, minus the page with the         signatures and dates and two conditions.

22 June 2012 – Work commences on Craighouse site with a trench being excavated.     The trench measures 3.0m (l) x 0.5m (d) x 0.3m (w). The trench is stated by Montagu Evansas being “within the area of the approved car park”. Despite being submitted and agreed only days before no work described in the tree protection plan, landscape management plan, or scheme of investigation for archaeological evaluation is performed, – other than a city archaeologist looks into the trench and notes he saw “significant root action”.

25 June 2012  –  Planning Dept. representative visits the Craighouse site and “noted signs of activity in the  potential car park area”

28 June 2012 – Council official writes to Montagu Evans to ask what work had been done and confirm “whether action has been taken to take up the consent” and if action has been taken, to provide evidence as to where, when and “what the work entailed”.

25 June 2012  – Expiry of the 5 year planning permission period from date of Final Decision Notice ( 26.06.07 )

05 July 2012   – Planning Dept. write to Montagu Evans to “accept the evidence that the planning permission  had been taken up within the statutory period”

6 July 2012 – Friends of Craighouse visit the archives again and see the actual planning consent for the first time – on top of the file.

We receive a letter from Planning in reply to enquiries to say there are no private files and that all documents are either on the portal or in the archive.

10 September 2012 – The full Section 75 Legal Agreement finally becomes viewable on the Planning Portal and is taken off  “private”. We understand that prior to this date the document had a status of not for public view, a highly contentious state of affairs.

There are a few things that are strange about this timeline:

  1. At no point are the Listed Building Consent and Planning Consent “live” at the same time, so there is no point at which the project can be legally completed.
  2. The paperwork for this planning application is unavailable to the public for a considerable period of time. We only find the actual consent after the work has started, and only get hold of a completed and signed version of the Section 75 agreement after months of searching and repeated letters and complaints to the planning department.
  3. Work starts by a property developer more than 10 years after the planning committee voted to allow work to start within 5 years “for the requirements of the university”. Work starts without any of the critical conditions (tree protection, landscape management, listed building consent, or archaeological investigation) being properly implemented.
  4. Nothing is referred back to the planning committee by officials, despite significant changes occurring to the original reasons for allowing the consent in the first place.
Posted in Planning process | Leave a comment

“High Fives” for Craighouse! Tell, blog, tweet, Facebook everyone you know craighouse-edinburgh-napier-mountgrange-development-info

Click to view

We have had a number of indications that the application may go in in the next few weeks.

We cannot know until or even if it will happen, but objections can be submitted by email, so if you are away, check the internet now and then or join our email list to keep informed. We will send out details of email address to write to when the time comes.

Raising Awareness

The Friends of Craighouse Save Our Craighouse campaign has done a huge amount to raise awareness of one of the largest proposed developments of protected green space for many years. Thanks to our members, we have gathered an incredible:

5500 local signatures!

  • Shops have displayed petitions and posters.
  • Hundreds of people gathered on the orchard to show their love of the site.
  • Politicians have made statements of support.
  • Morningside and Merchiston Community Councils have made statements and resolutions to oppose.
  • The Cockburn Association wrote to say they would oppose present proposals.
  • The Campaign has gathered media coverage and wide-spread support from across the city.

This  is a tremendous result. Thanks to all the people who support and love the site.

However, even now, two years after Napier University sold the Craighouse campus to a development consortium, there are people across wider Edinburgh who remain unaware of that this historic protected landscape is threatened let alone the scale of Mountgrange & Sundial’s proposed development and how what is proposed contravenes the Edinburgh Local Plan and is against the numerous protections and designations on the site. Many people are still unaware how this might impact their local green spaces and heritage sites through the powerful precedent that would be created by overturning these important planning designations.

Any decision the City of Edinburgh Council may take on the developer’s planning application will have consequences for generations to come, not only at Craighouse but for the increasingly threatened green space and parks throughout the city.  The estate at Craighouse has been existent for some 400 years, is it the right decision to allow excessive new build on such a historic and protected site, against policy and against all the protections?

It is time to start spreading the word further afield.

Many people from surrounding Morningside, Craiglockhart, Colinton, Shandon and even further afield use the grounds: for walking, as part of a visit to the city, to relax on summer days, for the spectacular views of Edinburgh over to the Castle and Arthur’s Seat, and it is an ever popular venue for hundreds to gather to watch the end of festival fireworks.  Due to the immense beauty of the estate, people often choose Craighouse as a wedding venue. As someone said to us – this is the Arthur’s Seat of South Edinburgh. Some use the grounds every day for walking or biking. Others maybe every week and others for special occasions or hill walks.

Mountgrange now own the entire campus site – including the woodland, the Local Nature Reserve and the parkland. Access remains a huge concern for the future.

So, we’re posing a challenge to you:

Tell five people about Craighouse!  They can be anybody that lives, works, or has an interest in Edinburgh – here’s some suggestions:

  • work colleagues or fellow students
  • your friends and family
  • people interested in buildings and landscapes or history
  • Wildlife groups or people who like wildlife and nature watching
  • your Facebook friends or Twitter followers
  • people you talk to at the library or local shops
  • your neighbours
  • hikers and ramblers
  • bikers and dog-walkers
  • residents associations or groups
  • school or parents societies
  • shops
  • Other green space groups – Friends of Parks or green spaces
  • or even people when having a conversation at the bus stop

You can talk to people in person, by text message, by phone, by email, instant message or notice board.  Perhaps point others towards our website, show them news articles and also the developers’ proposals. Or retweet, like or link to this post.

If you are unsure what to say, post or tweet a picture of the beautiful orchard and green space. We have many on our website here you can repost.

Here are some of the things that people frequently express concern to us about:

  • Craighouse is one of Edinburgh’s seven hills which should be protected.
  • That the green space, extensively used by local people for decades and designated Open Space in a Conservation Area of Great Landscape Value, is now threatened by development.
  • Kids, families, the elderly all enjoy this space and it is hugely important to the local community and the wider community of Edinburgh
  • The development sites are on areas designated Great Landscape Value,  Open Space in Conservation Area and Local Nature Conservation Site
  • Some of the most spectacular views in the city are put at risk due to the proposed development.
  • That the site is now owned by an offshore network of companies on the Isle of Mann
  • That the two senior partners in Mountgrange were the two directors of Mountgrange Capital plc, the company that spectacularly failed with the Caltongate development on the Royal Mile.
  • That in response to the local community expressing concern over the amount of new build last Sept, the revised proposals actually increased the amount of new build.
  • The local area cannot cope with the extreme increase of traffic and parking.
  • That the site will be covered in carparking as a result of all the extra cars and traffic – changing its natural feel.
  • That developers shouldn’t be trying to profit from building over protected green sites when there are many brownfield sites that need economic regeneration
  • That the development proposals are contrary to the Edinburgh Local Development Plan and should not even be entertained by the Council.

Together we can potentially spread the word out to thousands of people and groups across Edinburgh!

Craighouse is a site of citywide significance. People should know what is proposed before it is spoiled forever.

Thanks so much.

Posted in Uncategorized | Leave a comment

Craighouse Planning Articles: Skyline, Views Into the Site

SKYLINE: Views into the Site

One of the seven groups of hills which give great distinctiveness to the city….part of the basic structure and character of the city.” The hills give legibility and identity to the city and to its component parts. They provide outstanding backgrounds, settings, landmarks, and views in themselves and over a wide extent of the city and beyond.’ (The Craiglockhart Hills Conservation Area Character Appraisal)

In the second of our planning articles, we are looking at views. Craighouse is extremely important in terms of skyline and views.  So much so, we have split this article into two for ease and due to length: Views into the Site and Views Out of the Site. We will be posting Views Out of the Site very soon.

Situated on one of Edinburgh’s famous seven hills, which form a major part of the City’s character and a backdrop to views across the city,  Craighouse is a stunning, remarkably unspoilt hilltop sight prominent in views and aspects both locally and citywide.

It features significantly in the views from many of Edinburgh’s other hills, such as Arthur’s Seat, The Castle, Blackford Hill, the Braid Hills, as well as numerous high points and buildings around the city. It is also a stunning feature in many local views. The lush green lawns and fantastic buildings have been described as being like a “fairy dell” from these vantage points.

“A fairy dell” (one of our younger members)          Please click for proper view

The Craiglockhart Hills Conservation Area Character Appraisal:

“Views to the Hills from Arthur’s Seat, Calton Hill, Blackford Hill and Edinburgh Castle are also spectacular, in particular to Easter Craighlockhart Hill on which high quality Victorian buildings are set against a predominantly wooded hill

The Craighouse site retains its superb open aspects, most notably,  from the east.

Views to and from the site feature heavily in the Craiglockhart Hills Conservation Area Character Appraisal – an important document which we introduced in our last article.

Craighouse is protected as an Area of Great Landscape Value in a Conservation Area. The planning authority and the Scottish Executive are obliged to protect Conservation Areas from development that would adversely affect their special character, so that character, outlined in the Character Appraisal, is extremely important in planning terms. On views into the site it says:

“Outstanding…a superb hilltop site…still unspoilt” Historic Scotland

Another important document, The Edinburgh Council Survey of Gardens and Landscape 2007 says:

“Craighouse is significant as the site of Old Craig, for the buildings of the Royal Edinburgh Asylum and its associated social history…but perhaps most of all for its presence in views within Edinburgh and its accessibility to the people of the locality” (our bold)

“Views to and from the study area are of outstanding importance” (Simpson and Brown Conservation Audit for Napier University)

Old Craig – important historic feature viewable from across the city

Old Craig (the pink building right) is the oldest building on the site and is a prominent feature in many views into the site. The proposals for a huge “courtyard development” in front of it – taking out green space and woodland – would spoil not just the setting but destroy the views of this historic feature from outside the site. Large modern Oberlander blocks in the woodland opposite New Craig and more building around the listed buildings near Queens Craig would ruin the romance of the woodland backdrop and singular setting of New Craig (contrary to the Craiglockhart Hills Conservation Area Appraisal), while the orchard development would clearly spoil an important topographical feature (also contrary to the CHCA appraisal – see policies below). The excessive new-build currently proposed would urbanise what is now a romantic and important city feature.*

This picture (right) shows a part of the orchard development in the foreground with New Craig surrounded by more substantial amounts of new-build behind. The 4 or 5 storey apartment blocks will be clearly visible from outside the site and take out part of the woodland – which forms the backdrop to New Craig in views. The orchard is a key topographical feature and therefore to build at all here is completely contrary to policy.

The site can be viewed from the Crags – and is prominent in views from around Arthur’s Seat as a green “enchanted” hilltop

*note: commentary is based on the last set of proposals presented to the general public at exhibition. We cannot know what the plans will look like when submitted – however, the “alternative” masterplan at the exhibitions did not reduce the levels of new-build – which are clearly excessive – but placed the orchard development down the East side of the green space instead – again ruining the key protected area of the landscape that is the open green space, identified as one of the most important areas in terms of landscape character in the Simpson and Brown Conservation report and the spoiling views in and out of the site.

 

Relevant policies and key documents in relation to views both to and from the site:

  • ECLP Policy OS1 (Protection of Open Space) presumes against loss of open space unless it can meet five tests. The first test is that: ‘There will be no significant impact on the quality or character of the local environment’.
  • The Craiglockhart Hills Conservation Area Character Appraisal states that the essential character of the area is derived from its significant cluster of Victorian institutions set within a very high quality landscape and topographic setting.
  • It also states “high quality Victorian buildings are set against a predominantly wooded hill the woodlands emphasising the visual prominence of the site over the local surrounding area”
  • The Edinburgh Landscape Character Assessment describes it as a “prominent urban hill”, part of a series of distinctive hills in Edinburgh that contribute to form the character of the city.
  • Env 11 (Landscape Quality) presumes against development which would damage or detract from the character or appearance of the AGLV [Area of Great Landscape Value], prominent ridges or other important topographical features.
  • The Edinburgh Survey of Gardens and Designed Landscapes 2007 notes that the site is significant for its listed buildings and associated social history but particularly for its presence within views of Edinburgh and its accessibility for locals.
  • Edinburgh Skyline Study identifies Easter Craiglockhart Hill as a Key view to the Castle (S4b) which cannot be seen from the summit but from the open area to the south of the campus.
  • The Craiglockhart Hills Conservation Area Character Appraisal recognises: “The far-reaching and panoramic views.’
Posted in Uncategorized | 1 Comment

Holyrood Has Questions about Craighouse and Napier

Now, more on Craighouse from Holyrood, as reported in the Edinburgh Reporter yesterday.

Here is MSP for Edinburgh Southern, Jim Eadie’s question about Napier and Craighouse and a transcript of the ensuing exchange in Scottish Parliament Question time as posted on their website: CLICK HERE. We are delighted to see that questions are being asked at Holyrood about this matter and believe there should be a great deal more transparency from Napier.

Jim Eadie (Edinburgh Southern) (SNP):

14. To ask the Scottish Government what recent discussions it has had with Edinburgh Napier University regarding the future of the Craighouse campus. (S4O-01239)

The Cabinet Secretary for Education and Lifelong Learning (Michael Russell): I am not aware of any discussions. Universities are independent, autonomous institutions and, as such, the Scottish Government does not intervene in institutional matters such as decisions regarding their estates strategies.

Jim Eadie: I thank the cabinet secretary for that answer, but is he aware of the significant amount of local concern about the sale of the Craighouse campus by Edinburgh Napier University? It is seen as a valuable community asset. Notwithstanding Napier’s independence, does the cabinet secretary agree that the university has an obligation to achieve best value for the taxpayer, to ensure that all transactions are open and transparent, and to ensure that any assets are disposed of in a way that continues to provide benefit to the local community?

Michael Russell: Yes, I am keen that the indissoluble link between universities and the communities that they serve is recognised. The Scottish Further and Higher Education Funding Council requires colleges and universities to seek its prior approval for the disposal of publicly funded property when the proceeds are likely to exceed £3 million. As part of the approval process, the Scottish funding council requires colleges and universities to demonstrate that they have obtained an appropriate professional valuation from a reputable property agent. I will ask the council’s chief executive to write to the member to reassure him on this matter, and I will be happy to meet him as well.

—end of transcript—

Posted in Uncategorized | Leave a comment

Update on the Consent for New University Facility, Woodland Removal and Carpark

Just part of the fabulous panoramic views – with Arthur’s Seat and North Berwick Law

The Edinburgh Reporter published an article yesterday. It reports on questions in Holyrood about Napier and Craighouse and also that The Craighouse Partnership have applied to amend the conditions of the Section 75 agreement (attached to the consent we reported on two articles ago) in order to delay payments to the Council – perhaps indefinitely.

(See website link  http://www.theedinburghreporter.co.uk/2012/09/craighouse-campus-planning-discussions-continue/ )

More on that Holyrood question later – but for the moment, an update on the consent issue.

Some weeks ago, we revealed that the Craighouse Partnership had claimed to have activated a decade old planning consent. This consent was provisionally granted to Napier University in 2002, to build a 80,000sq foot Creative Arts building plus carpark, and was subject to a legal agreement being put in place between Napier and the Council. Oddly, while the terms of the legal agreement  were  laid out in 2002 the legal agreement itself was not signed by Napier until a full 5 years later in 2007. Yet another 5 years on, in May 2012, the Craighouse Partnership claimed to have activated the planning permission by commencing operations on the site. In essence, they dug a hole and filled it in again, but the council appear to have accepted this as a valid commencement.

Council say consent allows mature woodland to be removed and carparking put in

Both the developers and the council say that mature trees and parts of the woodland can be cut down as a result – even though there is no obligation on the developers to actually build the building they have gained planning permission for. We were also told they could put in a new carpark.

This demonstrates how careless waiving of planning protections for an individual “special case” (in this case “the needs of the university” in 2002) actually puts a historically important site under long-term threat of property speculation. This is a warning also for any future “deals” which can be exploited for other ends.

Below is a summary which will explain what has happened, the implications, and why this is so important.

Summary

  • The normal paperwork for a planning consent has been missing, inaccessible or very hard to obtain – in some cases for many years. It is only thanks to the tenaciousness of our volunteers that we have finally managed to track some things we were told didn’t exist down. The council officials gave the final consent more than 5 years after councillors originally provisionally approved it in 2002, 2007 being a time when Napier had already decided to sell Craighouse and abandon their plans for the site. Why did this happen?
  • The normal public oversight for a controversial planning consent like this does not seem to have been applied
  • The waiving of many of the conditions seems to have been pushed through in the last available weeks in June this year against many of the rules that are supposed to protect the site and against much of what was stated in the original consent and section 75 contract.
  • To “activate” the consent, the work must start within the rules in the consent. It did not, so legally, the consent should be treated as having expired.

Without challenging the council’s actions, the Craighouse site could be left as an unfinished building site for many years.

Section 75

Along with the planning permission to build a University Arts Facility, the Craighouse Partnership has also inherited the legal agreement originally signed by Napier and the conditions attached to it. Many of these conditions were designed to protect the site – and have apparently already been waived by the Council, without proper stated reasons.

Now, The Craighouse Partnership have applied to the council planners to relax the payment dates  – of the payments they are legally obliged to make, totalling £180,000. The delay may be many years, or the payments may never be made if The Craighouse Partnership  decides to sell the site on to someone else, as they have indicated they may do.  In their application to defer the payments dates, the Craighouse Partnership provide no materially significant reason for requesting the delay, other than to  say that “ the objective being to reduce the burden on developers in order to stimulate development “.

It is this issue that the Edinburgh Reporter article reported on yesterday (see link at top of this post).

What next?

Formal Complaint

We have notified both the Council and The Craighouse Partnership that we will be formally challenging the granting of the consent in 2007, the discharging of conditions on the site, the application for modification of the Section 75 agreement, and for the claim that there was a lawful start to the project.

We will be having a meeting with the Council officials about this matter next week and we hope to update you further then and also will go into some of this information in more detail for your information.

Rest of the Campaign Still on Track

We would like to reassure you that although this is a big and important issue – we are not taking our eye off the ball in terms of any forthcoming application from The Craighouse Partnership for their proposed housing development.

People continue to hand in petitions and we have over Five and a Half Thousand (5500) local signatures.

We have been working hard (hence our silence!) compiling research on planning and policies undertaken over the past year and have compiled a series of planning articles – this will cover everything from the protections, policies and key documents that affect the decision-making process to the enabling development and financial arguments, which have been researched at length. Much of this information will form the basis of the Friends of Craighouse objection letter, which we will also make available to everyone to view when the time comes. We hope this will form a useful basis of knowledge for anyone looking to find out more about the site, the policies and precedent – and prime us all for when the application goes in.

We cannot know in advance when the planning application will go in. Indications that the application will go in during the summer seem to be morphing to the autumn – the developers saying “a couple of months” to residents at recent invitation only meetings.

We cannot know when – but we will do our best to make sure everyone knows when it does.

Posted in Planning process, Press coverage | 4 Comments

Planning Article 1 – Designations, Protections and Key Documents

“outstanding…a superb hilltop site, still unspoiled” Historic Scotland

We have been compiling a series of articles about Craighouse and planning policy, which we will put permanently on the menu under “planning” for people to access. When the application goes in, there will be 21-28 days for the public to put in planning objections to the plans. It is best if these objections are put in terms of the material planning considerations – as this is what the planners must consider. We hope that these articles will help people get to know some of the policies and introduce the key documents.  We will also make available our own objection letter when the time comes.

It is interesting to note that these important protections on the site – the designations and  what is said in the Edinburgh City Local Plan – were not presented to the general public by the Craighouse Partnership on their exhibition boards at the two sets of exhibitions they held.

What becomes abundently clear when compiling and researching these articles is just how against policy the proposals are.

The Craighouse Partnership’s development proposals are contrary to the Edinburgh and Lothians Structure Plan, the Edinburgh City Local Plan, National Planning Policies and local policy documents. 

Craighouse has not been identified for new-build housing through the Development Plan process even though the plan was only adopted in 2010.

This, therefore, is a speculative application.

Overview

Craighouse is a spectacular green hill-top site on one of Edinburgh’s famous seven hills.

It contains Grade-A buildings of national significance set in beautiful rolling parkland and woodland grounds designated of Great Landscape Value. The site is in a Conservation Area,  contains a Local Nature Reserve and most of the site is protected as Local Nature Conservation Site.

As Historic Scotland observes above, the site is remarkably and unusually unspoilt, and, as such, particularly special and worth preserving. It is of huge amenity value to local people and citywide, has fabulous (and protected) views and is visible in views from all over the city. The site has enjoyed public access to the site for decades.

Protections

These are the protections that cover all or parts of the site the Craighouse Partnership want to develop:

  • Grade A listed buildings of national significance and their setting
  • Designated Area of Great Landscape Value
  • Open Space
  • Conservation Area
  • Local Nature Conservation Site/Local nature reserve
  • The whole site is a Candidate for Special Landscape Area (SLA) in the new Edinburgh Local Plan

The Edinburgh City Local Plan

What is being proposed for Craighouse is, as we said above, contrary to the Edinburgh and Lothians Structure Plan, the Edinburgh City Local Plan, National Planning Policies and local policy documents. 

Craighouse has not been identified for new-build housing through the Development Plan process even though the plan was only adopted in 2010. It is a candidate for Special Landscape Area (SLA) in the new plan which is due to be adopted in a few years.

The Edinburgh City Local Plan at 5.6 says:

 This policy seeks to protect all open spaces, both public and privately owned, which contribute to the amenity of their surroundings and the city, which provide or are capable of providing for the recreational needs of residents and visitors or which are an integral part of the city’s landscape and townscape character and its biodiversity… It will be more important to protect open spaces in the future, as the population of parts of the city increases and brings added pressure on existing resources.

(Our bold.)

The Craighouse Partnership likes to argue it is now private land. However, the Edinburgh Local Plan states very plainly that both public and private land designated Open Space should be protected. The Craighouse Partnership knew this when they bought the site. We will be returning to the Edinburgh Local Plan and examining the numerous policies contravened by these proposals in subsequent articles.

Conservation Area Character Appraisal

The Craiglockhart Hills Conservation Area Character Appraisal  is a very important document in planning terms and will inform the decision-making process so we will be referring to this a lot in coming articles:

“The protection of an area does not end with conservation area designation…The planning authority and the Scottish Executive are obliged to protect conservation areas from development that would adversely affect their special character.”

Here are a few quotes from the Craiglockhart Hills Conservation Area Character Appraisal gives you a flavour of  just how important and unique this site is, the character that must be protected – exemplified by Craighouse as a whole –  and just why this site is so heavily protected:

From the Craiglockhart Hills Conservation Area Character Appraisal.

“ a mosaic of habitats which are exceptional within a city environment”

“significant cluster of Victorian institutions…within a very high quality landscape and topographical setting”

“The Craighouse site retains its superb open aspects, most notably, from the east”

“extensive panoramic views of Edinburgh, across the Firth of Forth and to the hills beyond.”

“Views to the Hills from Arthur’s Seat, Calton Hill, Blackford Hill and Edinburgh Castle are also spectacular”

“high quality Victorian buildings are set against a predominantly wooded hill, the woodlands emphasising the visual prominence of the site over the local surrounding area”

The Edinburgh Council Survey of Gardens and Designed Landscapes 2007:

This survey was undertaken to survey areas under threat from development and its findings are also considered important in terms of planning and decision-making. It says:

“Craighouse is significant as the site of Old Craig, for the buildings of the Royal Edinburgh Asylum and its associated social history…but perhaps most of all for its presence in views within Edinburgh and its accessibility to the people of the locality”

Conclusion – for now

We hope that serves as some introduction to how important Craighouse is in planning terms and some of the documents we will be looking at in subsequent articles.

Allowing the proposed excessive new-build development over the protected landscape of such an important site would set a precedent that would affect the future of every green and historic site across Edinburgh.

Craighouse is no ordinary site. It is unusually unspoilt historic site of Great Landscape Value on Edinburgh’s seventh hill and a key feature of our city. This fabulous historic green hill site must be preserved.

Posted in Planning process | 5 Comments